·RFP for Environmental Consultant Services transmitted - 3/11/10
· CRA/LA staff and Steering Committee members begin drafting Redevelopment Plan goals and objectives - 4/27/10
·City Planning Commission adopts Preliminary Plan - 6/10/10
·The contract for Environmental Consultant Service is executed - 6/25/10
Activities
The Plan Amendment consultant completed the physical blight survey and GIS has uploaded approximately 60% of the data into their database system.
GIS staff is reviewing all survey forms for errors and as needed, the Consultant is currently correcting any omitted or incomplete information on the forms.
CRA/LA continues to meet with the Steering Committee, completing a draft of the Redevelopment Plan goals and objectives and beginning to draft the section on development controls and the initial 5-Year Implementation Plan.
The draft Notice of Preparation was sent out on August 27th and the EIR scoping meeting has been scheduled for 9/15/10. Comments on the Draft EIR must be recieved no later than September 28, 2010.
Next Steps
Complete data entry for physical blight survey.
Complete economic blight data collection and begin compiling both the physical and economic blight data into a draft report.
Draft Redevelopment Plan permitted land uses and development controls.
Execute contract for the leagal description.
Transmit Statement of Preparation to Taxing Entities.